Commercial Projects
Education Projects
Industrial Projects
Recreation Projects
Residential Projects
Science, Health &
Community Projects
Heritage Projects

Education Projects

BER Government Schools Project, Melbourne
Construction and fit-out of school buildings (10) predominantly in the Brunswick and Coburg area.

Project Value: $13mil Client: Dept of Education and Early Childhood Development
Architect: Various – Hayball. Suters. GrayPuksand. Completion Date: August 2010 to
June 2011

University of Melbourne Wilson Hall, Parkville
Roof replacement in a building with a heritage overlay (Wilson Hall).

Project Value: $270k Client: University of Melbourne
Architect: Lovell Chen Completion Date: February 2011

Caulfield Grammar School, Caulfield
Renovation works to existing building.

Project Value: $1.1mil Client: Caulfield Grammar
Architect: John Gribble Architects Completion Date: January 2011

Lauriston Girls' School Montrose House, Armadale
Extension and refurbishment woks at historic Montrose House.

Project Value: $2.6mil Client: Lauriston Girls' School
Architect: Design Inc Completion Date: November 2010

St John's Primary School, Clifton Hill
Renovation of an old hall within a heritage structure. Refurbishment of a heritage façade.

Project Value: $2.9mil Client: Catholic Education Office
Architect: Bradbury Dicker Group Completion Date: August 2010

Back to Top

Resurrection College, Keysborough
Development of a new library and multi-purpose facility.

Project Value: $1.7mil Client: Catholic Education Office
Architect: Meaden Architects Completion Date: April 2010

Camberwell Grammar Norge Junior School, Balwyn
Complete refurbishment of ground floor library. Addition works to the first floor.

Project Value: $2.5mil Client: Camberwell Grammar School
Architect: Peter Crone Architects Completion Date: March 2010

Fintona Girls' School, Balwyn
New double storey structure built between two existing buildings.

Project Value: $800k Client: Fintona Girls' School
Architect: Peter Crone Architects Completion Date: February 2010

Melbourne Grammar Grimwade House, Caulfield
New build and refurbishment works at Melbourne Grammar junior school campus.

Project Value: $5.8mil Client: Melbourne Grammar School
Architect: Peter Elliot Architects Completion Date: September 2009

University of Melbourne Grainger Museum, Parkville
Refurbishment and alterations to heritage building.

Project Value: $2.5mil Client: University of Melbourne
Architect: Lovell Chen Completion Date: March 2009

Back to Top

Monash University Manning Building, Parkville
Design and construct contract to build the Pharmacy College at
Monash University.

Project Value: $10.7mil Client: Plenary Group
Architect: Techne Architects Completion Date: August 2008

University of Melbourne Storey St Wall, Parkville
Heritage Wall rebuild.

Project Value: $800k Client: University of Melbourne
Architect: Lovell Chen Completion Date: May 2008

University of Melbourne Building 250, Carlton
New building and tie into existing facility.

Project Value: $1.8mil Client: University of Melbourne
Architect: Six Degrees Completion Date: May 2007

AMI Cooking School, Carlton
Refurbishment works.

Project Value: $700k Client: AMI Education
Architect: Lindsay Holland & Assoc Completion Date: March 2007

Trinity Grammar Watson Building, Kew
Alterations works.

Project Value: $800k Client: Trinity Grammar
Architect: Crone Ross Architects Completion Date: January 2003

Back to Top

Loreto Mandeville Hall, Toorak
New multi-purpose sports centre and art facility.

Project Value: $7.2mil Client: Loreto Mandeville Hall
Architect: Crone Ross Architects Completion Date: January 2003

Trinity Grammar Science & Technology Centre, Kew
Construction of a new science and technology centre at Trinity Grammar.

Project Value: $6mil Client: Trinity Grammar School
Architect: Crone Ross Architects Completion Date: January 2002